PLC 2011 - Three-Phase Construction



Clock Hours: 132

Delivery Mode
on-ground

Course Description:
This course covers how to install guys to support a utility pole, as well as how to install the equipment on the pole to support conductors.  It includes the installation of cross-arms, transformers, and conductors.

Student Learning Outcomes:
  1. Describe three-phase construction.
  2. Identify the hardware used in aerial framing.
  3. Using the standards manual, identify materials, assorted pole hardware, and support arms. It includes the installation of cross-arms, transformers, and conductors needed to perform aerial framing on:
    1. A single cross-arm
    2. A double cross-arm
    3. A dead triple cross-arm set
    4. An outrig arm
    5. An alley arm
  4. Describe, assemble, and install guys.
  5. Perform an aerial framing procedure as defined by the instructor.
  6. Hand-pull three-phase primary conductors, dead end, and sag.
  7. Explain how to install a transformer and connect conductors.