PLC 2011 - Three-Phase Construction
Clock Hours: 132
Delivery Mode on-ground
Course Description: This course covers how to install guys to support a utility pole, as well as how to install the equipment on the pole to support conductors. It includes the installation of cross-arms, transformers, and conductors.
Student Learning Outcomes:
- Describe three-phase construction.
- Identify the hardware used in aerial framing.
- Using the standards manual, identify materials, assorted pole hardware, and support arms. It includes the installation of cross-arms, transformers, and conductors needed to perform aerial framing on:
- A single cross-arm
- A double cross-arm
- A dead triple cross-arm set
- An outrig arm
- An alley arm
- Describe, assemble, and install guys.
- Perform an aerial framing procedure as defined by the instructor.
- Hand-pull three-phase primary conductors, dead end, and sag.
- Explain how to install a transformer and connect conductors.
|
|